House Construction Planning
Excavations and Shoring
For the construction of the building, general excavations are always made. The depth is determined at the level of stable ground.
Shoring is made with usable materials extracted from the excavations.
If insufficient, additional materials are used. |
1 week |

|
Foundations
Before the groundwork (depending on the quality of the ground) and after the excavations are completed, we add a 10 cm layer of C12 (B160) slurry concrete for the better placement of the reinforcement mesh.
The construction of the foundation is made according to the Static study and the designs of the Civil Engineer. When the building has a basement below ground level, the walls are made of concrete according to the Static study and the designs of the Civil Engineer, and the reinforcement is made conform to the Greek law.
If there is an adverse water table in the subsoil, we recommend, during the casting of the concrete, mixing the concrete with a waterproofing solution. After the removal of the formwork, a coating to the exterior side and to the area under the ground with ISOMIX (one of the best sealant diaphragm with great elasticity).
The part of the walls above the ground will be coated with plaster or natural stones, as described. |
2 weeks |

|
Quadlock and reinforcement
The construction above the basement is made with the Structural System Quadlock in combination with a steel skeleton.
The QuadLock elements are placed between the solid steel skeleton and filled with high quality concrete C20/25.
In several cases we use a normal reinforcement, building the steel columns (into the Quad Lock walls (see picture). |
1 week |


|
Concrete for each floor
Non supporting, ground level.
After the connection of the supporting beams we put a structural reinforcement, T92, all over the surface, together with concrete C12/16, minimum 15 cm.
Supporting, basement and floor Steel reinforcement according to the static calculation of the responsible engineer. |
1/2 week |

|
Plumbing, electricity and heating works
All installations (electrical, plumbing, heating) are placed after a study performed by our mechanical engineer, in co-operation with the client.
Electrical: All basic installations with high quality materials, conduit, cable, wires, placing of sockets and switches.
Plumber work: All basic installations for water supply and drainage, placing of all sanitary ware, solar water heater and a high-pressure device for the water tank.
Central heating: All the necessary equipment for the electric floor heating or electric heating panels is installed. |
4 weeks |



|
Interior walls and plastering works
INNER PARTITIONS:
They are constructed of YTONG blocks according to the design, in some cases we will use the dry wall system.
PLASTER - COATING:
All the walls and the inner partitions are coated with materials of an excellent quality. |
6 weeks |

|
Doors & Windows
Are of an excellent ALUMINIUM or PVC quality with high technology and available in a wide range of colors and models. |
1 week |

|
Floors
The laying of floor tiles, marble and marble finished staircases is included in our package price. |
1 week |
.JPG)

|
Painting
The full painting of the house, inside and outside, with high quality materials from well-known international companies, is included in our package price. In some cases we put a high quality plaster with integrated color so that the house has never to be painted again anymore. |
2 weeks |

|
Finishing
We also undertake any other work, needed for the completion of the construction, such as landscaping, fences, pergolas, pools (SOLID POOL) and gardens.
Our clients choose interior doors, sanitary ware, floor finishes, fixed items, kitchen, banisters and fireplace, the cost of which is included in the package price. |
2 weeks |


|
Quadlock Construction - Concrete Construction |
|